 |
Great River Energy must continuously
update and expand its transmission system to serve the
growth in our area. We own more than 4,400 miles of transmission
power lines. These lines cover about 60 percent of Minnesota and run into North Dakota and Wisconsin.
|
| |
| Minnesota |
|
Project |
Description |
Status |
| |
Great River Energy, power supplier to Stearns Electric Association, is planning to upgrade an existing 69 kV transmission line from City of Richmond six miles north to Stearns Electric's Farming distribution substation located in Farming Township. |
GRE plans to obtain approval for this project through Stearns County, and will begin the permitting process in early 2008. Design and construction of the project is scheduled for summer and fall of 2008, with project completion in December 2008.
|
| |
This project and other nearby 115-kilovolt
projects will provide an outlet for 1,000 incremental megawatts of wind
energy and enhance south Metro reliability. This project is part of CapX
2020, an innovative joint initiative to ensure long term electric reliability
for Minnesota and the surrounding region in the future. |
Great River Energy and other CapX 2020 utilities
filed a certificate
of need with the Minnesota Public Utilities Commission August 16.
The CapX Brookings, S.D.–Southeast Twin Cities Notice
Plan was filed with the Minnesota Public Utilities Commission on June
9, 2006.
|
| |
Itasca-Mantrap Cooperative Electrical Association
(Itasca-Mantrap) is an electric service provider in Hubbard County, Minnesota.
Because this area has seen unprecedented growth in demand for electricity
in the recent years, Itasca-Mantrap is planning to build a new substation
to meet increasing electrical needs. |
Permitting activities will begin during
the winter of 2007.
|
| |
Great River Energy serves customers in Crow
Wing County, the rapidly growing Lake Mille Lacs area and surrounding
rural areas. The new transmission line is needed to meet increasing demand. |
The Minnesota Public Utilities Commission
approved the certificate of need and route permit for the project on January
25. Project design and easement acquisition are now underway. |
| |
A new distribution substation and transmission
line need to be constructed to support growing electricity demand in the
area around Longville. The substation will be located in Longville, and
will be fed from a transmission line originating south of Wabedo Township.
Feeding the substations from other directions has been evaluated but all
other options west, north or east are not viable alternatives because
of system deficiencies. |
After reviewing numerous routes and soliciting
feedback from governing agencies and local property owners, a final route
has been established. Tree clearing and construction are planned to commence
this summer, with project completion by the end of 2007.
|
| |
Great River Energy serves customers in Pequot
Lakes, Pine River, Backus, Hackensack, Park Rapids, and the surrounding
rural areas. Based on historic and projected load growth rates, the existing
transmission system will not be adequate to maintain acceptable voltage
levels, which may jeopardize power delivery in these areas. |
The Minnesota Public Utilities Commission
issued a route permit for the
Badoura project on October 31. Great River Energy will now proceed with
project design and easement acquisition.
Great River Energy submitted a route
permit application on March 14. The Environmental Assessment is now
available. |
| |
Great River Energy serves customers in the
Vermilion Lake area, Tower, Ely, Winton, Babbitt, and the surrounding
rural areas. Based on historic and projected load growth rates, the existing
46 kV transmission system will not be adequate to maintain acceptable
voltage levels, which may jeopardize power delivery in these areas. |
The Minnesota Public Utilities Commission
issued a route permit for the Tower
project on August 1. The Western route proposed by the citizens is the
route that was permitted by the Commission. Survey of the line is underway
in fall, 2007. |
|
Great River Energy, power supplier to Crow
Wing Power, proposes building a nine-mile 115 kV transmission line to
provide a connection between an existing 115 kV line located in southern
Baxter and Minnesota Power's existing 115 kV line that extends along the
northerly segment of East Sylvan Township. |
The project will be permitted through the
Minnesota Public Utilities Commission. The transmission line route permitting
process will occur during the fall, 2007/ winter, 2008. |
| |
Minnesota Valley Electric Cooperative is
the electric service provider in and around Jordan, Minnesota. Because
this area has seen unprecedented growth in both the residential and commercial
sectors in recent years, MVEC is planning to build a new St. Lawrence
Substation to meet increasing electrical needs. |
Great River Energy filed notice of intent
to seek local approval of the project to the Minnesota Public Utilities
Commission November 1.
|